The Virginia fact sheet

Numbers with
the context attached.

A dated guide to data center scale, electricity, water, and economic impacts. Read each measure within its own geography and time period.

Evidence reviewed September 9, 2026

01 / Scale

Start with
what is being counted.

A campus, a building, and a megawatt are different measures. Construction and operating status also matter.

Statewide baseline · JLARC 2024
150

sites

340

buildings

About 80% of the industry was concentrated in Loudoun, Prince William, and Fairfax. This is a historical baseline, not a 2026 live count.

JLARC, pp. 5–6

02 / Electricity

The energy trend
is already visible.

Energy is the amount used over time. Peak demand is the highest draw the grid must accommodate at a particular time.

Virginia commercial sector · 2019–2025+30mMWh, approximately

Growth in annual electricity sales

EIA attributes much of this growth to data centers, alongside electrification. It is not a direct measurement of data center consumption alone.

2025 preliminary; 2019–2024 final in this analysis.

EIA · Virginia electricity growth
Observed · PJM Dominion zone

Two recent seasonal peaks

Whole-zone load across customer types. These are different seasons, not a data-center-only trend.

EIA · May 2026
What does a megawatt mean? Try an example →

03 / Water

The statewide total
is only the beginning.

A responsible local discussion also asks where water comes from, how cooling works, and what happens on the hottest or driest days.

Research identifies cooling design, climate, hardware, utilization, and the water used by electricity generation as key variables. There is no universal water-per-workload figure.

Berkeley Lab · Water use of data center workloads
Virginia · 2023 estimate2.1billion gallons

Industry water use; just over one-third reclaimed.


JLARC had data for the large majority of facilities, not every building. Annual totals do not describe peak-day demand.

JLARC, pp. 62–63

04 / Economic impact

Count the benefits.
Define the jobs.

Tax revenue, construction employment, and ongoing operations describe different benefits. A useful discussion keeps them distinct.

Virginia · Modeled annual average, FY2021–FY2023

Estimated jobs supported by phase

These estimates include direct, indirect, and induced jobs. The combined 74,000 is not a count of permanent on-site employees.

JLARC / Weldon Cooper Center, pp. 14–15
Loudoun County · FY2026$1.2billion

County-reported data center real and personal property tax revenue.

Budget projection · FY2027$1.3billion

Projected data center revenue in the adopted county budget.

One county’s experience; these are revenue figures, not statewide net-benefit estimates. Loudoun County · Data centers by the numbers

05 / Reading the outlook

A forecast is
a range of possibilities.

Demand depends on future equipment, utilization, efficiency, and projects actually entering service. A scenario is not a completed facility or a guaranteed outcome.

United States · Modeled 2030 electricity use

Berkeley Lab’s national outlook

2025 Update, published June 2026

521Low scenario
649Reference case
843High scenario
0450900 TWh/year

The range combines modeled uncertainties. These are U.S. totals, not Virginia figures or guaranteed growth.

Berkeley Lab · U.S. energy report, 2025 update